Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

The SLD is automatically generated based on the equipment and configurations specified on the design page.

Adding notes

You can add extra information to the SLD by adding notes. With your mouse above the SLD, right click, and the note box will appear.

Grid protection device / Secondary Protection

To include a grid protection device on the SLD, first make sure that

  1. First add a grid protection device

exists in
  1. to your inventory.

If not, you can
  1. You can add one from the product library, or create a custom item in your inventory and assign the item category as “Grid protection device”.

When you select a
  1. On the pricing page, add the grid protection device

in a
  1. to the quote, and it will automatically be added to the SLD.

  1. To add the grid protection settings for a specific device, go to Inventory > search for the unit, and click the edit icon.

    1. In the Description field, type in the grid settings.

Those settings listed in the Description will now appear in the SLD.

Automatic Transfer Switch, aka Backup box

The ATS symbol will be added to the SLD if Grid Configuration is set to
  1. On the Solar & Battery designer page, in the Grid Configuration section, select Back-up (ext). This will add the ATS / Backup relay symbol to the SLD

  2. Add a Backup box / ATS to your inventory, either by adding one from the Product library, or creating a custom item and assigning it the category ‘Automatic Transfer Switch / Back-up’

  3. On the Pricing page, add the ATS / Backup box to the quote. The model name of the ATS will

also
  1. now appear in the text boxes below the SLD

when an item with category ‘Automatic Transfer Switch / Back-up’ is selected in the quote
  1. .

Image Modified

Image Modified

Export limit device / Energy meter

  1. Add

any
  1. an Energy Meter to

the design page and the CT and data connection will be shown to satisfy this requirement. If you don't have any appearing in the select list, you can add them from the Product Library ‘General Components’ tab, or just create your own inventory item with the category set as 'Energy meter'.
  1. your inventory, either by adding one from the Product library (select the ‘Other’ section), or creating a custom item and assigning it the category ‘Automatic Transfer Switch / Back-up’

  2. On the Solar & Battery designer page, in the AC section, select the Energy Meter. This will add the energy meter symbol to the SLD, and add the meter to the quote price.

Image Added

Image AddedImage Added

Sub-board / distribution board

To add a sub-board, simply specify the length of the sub-main cable in the AC cable section of the Solar and Battery design page. If the sub-main cable length is >0m , then a sub-board will be added to the SLD.

AC-coupled off-grid

Not all system configurations have SLDs automatically produced. We are still working on AC-coupled and AC/DC coupled off-grid.